Excellent progress has been made on works to restore the Menai Suspension Bridge. Following the replacement of all 168 hangers on the bridge it has been confirmed that phase one of the programme will be completed on schedule. The bridge will reopen on Saturday 2 November [00:01hrs]. |
The start of phase two works, which amongst other things involves the repainting of the bridge, will be paused for four months (November 2024 – February 2025) to allow for the full reopening of the bridge, including the lifting of the 7.5 tonne weight limit, over the winter period. This will not impact the schedule for the 200th anniversary in January 2026.
This will bring a number of benefits including:
The Cabinet Secretary Transport and North Wales, Ken Skates said,
Before the start of phase two works a period of communication will take place with the general public and stakeholders. |
Discover more from Carmarthenshire News Online
Subscribe to get the latest posts sent to your email.